A CHP plant based on two MWM gas engines and two boilers provide hot water to 3,105 apartments in 50 multistory blocks, two schools, three kindergartens, and two hospitals for heating and usage purposes in one of Tashkent districts.
Thanks to the new plant, power fluctuations are no longer an obstacle to the textile production processes. The hot water produced during the production process is used to heat a 9-hectare greenhouse.
The 2.3 MW cogeneration project for a textile enterprise was commissioned in 2022 with a waste heat recovery steam boiler.
A modern cogeneration plant has been commissioned in the Shon-Shukhrat neighborhood of the Almazar district. This investment project, developed in cooperation between JSC Thermal Power Plants and the Turkish company Iltekno, was implemented using energy-saving technologies.